Most build-vs-rent comparisons stop at the numbers. This one follows the calendar. Build your own central production unit and year one is spent assembling a design team, waiting on quotes and managing contractors, with production starting around month 13. Rent a fitted CPU and you’re usually producing by month four, and the rest of the year goes on making money from it.
It’s one of the industry’s better-kept secrets that you can rent a fully fitted production kitchen. Most people, from consultants to ops managers, will tell you a CPU has to be custom built for your business. At Karma Kitchen, we provide a fully fitted unit and then adapt it to order before you move in.
I’ve seen both sides of this, building kitchens for my own catering business and for nearly 200 others. So rather than compare costs again, this piece walks through year one month by month: first building your own CPU, then moving into one of ours.
Year one: building your own
Months 1 to 3: the site, the lease and the team
The first few months are spent finding the right site, and that part is comparable whichever route you take. Once you’ve found a location, you’ll negotiate the rent. Expect a base rent of roughly £20 to £50 per square foot. That figure won’t include services, rates, service charge or utilities. Most of those are fixed by the landlord and you often won’t see them until later. We break down that hidden half in what your rent doesn’t tell you.
The lease may include a rent-free period or stepped rent to cover your building works. Depending on the lease length, that could be a few weeks or several months. Negotiating it typically takes two to three months.
While that’s happening, you’ll need information from the landlord to plan the works. How much power does the building have, and is it three-phase? Does it have its own water supply and meter, and gas if you need it? Where are the main drainage points, and how deep are they? You’ll also need to commission surveys, such as a CCTV drainage survey, or a structural survey if there’s a mezzanine, to find out what load it can take. These are the questions that decide whether a unit can take your volume at all, which we cover in extraction, power and drainage.
This is the time to appoint a project manager to assemble your consultants and surveyors. A good one costs £10,000 to £30,000, and it’s money well spent. Without someone coordinating, this stage overruns, your rent-free period runs out, and you’re paying rent on a building you can’t use yet.
You’ll also need an architect or kitchen designer, and a services engineer to design ventilation, power, plumbing, heating and cooling. Larger projects need a structural engineer and a quantity surveyor too. You’ll also appoint a building control surveyor, who makes sure the works meet building regulations.
By the end of month three, you should have a signed lease and a project team.
Months 3 to 8: design, and the first real price
This is the main planning phase. On a large CPU, your architect coordinates information from every consultant, and layouts are usually agreed with you by month six or seven. From then on, the work is about preparing everything a contractor needs to price the job.
The design comes in packages. The architect covers walls, floors and structure. The services engineer covers electrics, ventilation and pipework. The structural engineer covers sub-ground drainage, lifts and structural works. Together they produce coordinated “stage 4” drawings and a schedule listing everything to be bought or built. That pack goes out to three or more contractors.
By month six, or month eight at the latest, the schedule is out to tender. Unless you’ve used a quantity surveyor, this may be the first time you find out what the project will cost. It’s an uncomfortable thought: eight months in, lease signed, and only now do you see the real number. The quotes will also tell you how long the build itself will take.
After some negotiation on cost and timeline, you’ll appoint a contractor. The contract takes about two weeks to finalise, often followed by a two-week mobilisation period. Use that time to arrange construction insurance. It’s separate from your building or business insurance, which usually won’t cover construction works.
The contract will set out a payment plan, which is how the builder manages their cash flow. Make sure you can meet it, because a missed payment means delays.
Months 9 to 11: the build
Nine months in, the hard hat is finally on. By now most design decisions are made. If kitchen equipment isn’t in the building schedule and you’re sourcing it yourself, now’s the time to order it and plan installation and commissioning around the builder’s programme.
On site, the builder is held to time and budget by their contract, and by you and your project manager. Your consultants will inspect the work regularly to check it follows the plans. Those visits are usually charged individually, so leave room in the budget.
For a medium to large CPU built by an experienced contractor, 12 to 14 weeks should be enough for the main works.
Months 11 to 13: sign-off and move-in
The site should be ready around month 12. The final month is snagging, commissioning, and the builder’s clean and final clean before your equipment goes in.
Before you can open, building control carries out its final inspection and issues a completion certificate.
In the month you move in, you’ll put in place your fire safety, accessibility and pest control arrangements: fire routes, signage and extinguishers across the site, and an appointed pest control contractor. You’ll also install wifi, set up utilities and waste contracts, and start paying business rates. These are a significant part of a new site’s cost base. Utilities alone can approach your rent bill, so give your team time to work with brokers and fix the price. If your landlord supplies utilities, you’ll be on whatever contracts they’ve negotiated.
By month 13, you should be fully up and running in your new CPU. Only around now will you know the full cost: build, consultants, surveys and equipment combined. Contractors and consultants raise cost variations right up to completion, and they can move the budget materially. That’s why a sizeable cash contingency matters.
Year one: moving into a Karma Kitchen CPU
Months 1 to 3: the lease and the plan
Finding the right unit takes just as long whether you’re looking at empty warehouses or a provider like us. What changes is everything after you choose.
Our leasing process normally takes just under two months. CPU leases usually run for a minimum of two years, with a break clause and no rent increases during the term. Our leases are standardised, written in plain English and designed for food operators (more on that in lease or licence). We don’t usually offer long rent-free periods, because there’s no long downtime to cover. Larger customers often need sign-off from several stakeholders, including finance and sometimes the board. On a longer lease, the contract value can cross internal thresholds that need extra approval.
CPUs work differently from our smaller kitchens. Every CPU is configured individually, so we price each one project by project, at a lower rate per square foot than our all-inclusive kitchens. Services are separate and you choose which we run. You pay for what you use, at rates negotiated across all our sites: electricity, water and rates, plus a service charge covering fire safety, wifi, pest control, waste and more. Our sales team sets all of this out during the lease process. You don’t set up any contracts yourself, and everything works from day one.
Meanwhile, our facilities and operations team works with yours on the layout. There are no architectural drawings. It can be as simple as dropping labelled blocks onto our floor plan, or talking us through how you work. We’ll ask for your equipment list and discuss what you need. Our units already have ventilation, the right power, water, drainage, and production-standard floors and walls. You don’t need a design team or specialist consultants. Planning usually takes about a month, and we work out how to deliver it before your move-in date.
You’ll sign in month two. Before you do, the final plans are agreed and you get a clear price for anything specific to your operation. You know the cost before you commit. The unit itself, with its extraction, power, drainage and production-standard fabric, is already built at our cost. Changes made only for you, such as moving equipment, adding supplies or structural work, are recharged. They typically cost from a few hundred pounds up to £30,000 for complex jobs. For comparison, consultants and surveys alone on a self-build can cost over £20,000.
We usually carry out these works ourselves, charging a 10% fee in line with most construction companies. We combine them with any general works on the unit, so there’s one team and one programme, which cuts both cost and time. The lease can include a rent-free period while that happens.
How long it takes depends on how much changes. A standard kitchen with us can be producing within ten working days of signing. A CPU that needs alterations takes a little longer. Our build for Compass Group, with 8 metres of new extraction, a walk-in cold room and plumbed-in combi ovens and bratt pans, took four weeks. That’s possible because we’re both the landlord and the builder. We know the building, and the team to deliver is already in place.
Months 3 to 4: moving in
Once the lease is agreed and the deposit is paid, most CPU customers move in around three months after first contacting us and seeing a site.
Month three brings a week of testing and commissioning, plus light snagging your own team can handle without a specialist. We hand over a clean, working space your team can start producing in on their first or second day.
Services, utilities, pest control and waste are already running. In your first week, you’ll have an induction with your site manager covering fire procedures, waste processes and how the site works. You’ll get a call sheet for issues and emergencies and a site handbook, and your site manager stays on hand for questions.
Month 4 onwards: running the business
By month four, your team is producing in your new CPU. For most of our clients, the rest of the year goes on optimising production and using the site to grow revenue. They usually carry less debt too, because their capital outlay was a fraction of a build’s. For the full numbers, see build vs rent: the real cost of a CPU in London.
The same year, two very different businesses
Lay the two timelines side by side and the gap isn’t only about cost. The self-build operator spends year one running a construction project: assembling consultants, waiting eight months for a real price, managing a contractor and setting up a dozen supplier contracts. They start producing around month 13, often before they know the final bill. The operator who rents spends year one making food: producing by month four, with the price agreed before signing and the services already running.
We’ve built six sites of varying sizes and moved nearly 200 businesses into them over the past six years. That’s given us a clear view of what both routes really take. If you’re weighing the decision yourself, should we build a kitchen? covers the strategic side.